ECM & QECP guides and FAQ

Direct answers to the questions developers, contractors and QPs most often ask about Earth Control Measures, QECP and PUB submission in Singapore.

What is ECM in Singapore construction?

Earth Control Measures (ECM) are temporary works — silt traps, sediment ponds, perimeter bunds and wash-down areas — that stop soil, silt and construction debris from entering the public drainage system and waterways in Singapore during earthworks and site clearance.

When is an ECM plan required?

An ECM plan is typically required whenever a project involves earthworks, site clearance, piling or excavation with a risk of silt-laden runoff — commonly requested by PUB during the drainage submission stage, or where the site discharges to a public drain or watercourse.

Common PUB comments for ECM submissions

Recurring PUB comments cover unclear discharge points, missing sediment trap sizing calculations, absent maintenance and inspection schedules, and drawings that are not coordinated with the civil, architectural and construction programme.

ECM site inspection checklist

Before rain, check silt traps and bunds are clear and functional; during heavy rain, monitor discharge points for turbidity; after rain events, desilt traps, repair eroded bunds and log inspection findings. See the full ECM inspection checklist.

ECM & QECP FAQ

Short, direct answers for both visitors and search engines.

Q

What are Earth Control Measures?

Earth Control Measures (ECM) are the physical and procedural measures - silt traps, sediment basins, cut-off drains, treatment units - used to stop silty stormwater runoff from construction sites entering Singapore's public drains.

Q

What does ECM mean in Singapore construction?

In Singapore, ECM refers to the erosion and sediment control system registered with PUB under the Sewerage, Drainage and Coastal Protection Act 1999 for a construction site.

Q

What does a QECP do?

A Qualified Erosion Control Professional (QECP) prepares or endorses the ECM plan, ensures it meets PUB's requirements, and remains involved through inspection, monitoring and close-out.

Q

When should a QECP be appointed?

Generally as soon as a project's earthworks, site clearance or excavation risk silty runoff, and before the ECM plan is submitted to PUB. Project-specific assessment is recommended.

Q

Does my residential A&A project require ECM?

It depends on the scope of works and site conditions; projects involving substructure or superstructure construction commonly require an ECM plan, but this should be assessed for your specific project. See our residential A&A case study.

Q

What documents are needed for an ECM submission?

Typically the ECM plan and drawings, QECP endorsement, and supporting site information; PUB may request additional documents depending on the project.

Q

Who endorses an ECM plan?

A QECP endorses the ECM plan before it is submitted to PUB for approval.

Q

Can ECM works begin before PUB approval?

No - the ECM must be implemented in accordance with the QECP-endorsed, PUB-approved plan before work commences.

Q

What happens if the approved ECM arrangement changes?

The QECP must review the change and re-submit the ECM plan to PUB for approval before the change is implemented on site.

Q

How often should ECM be inspected?

Inspection frequency depends on the approved ECM plan and site conditions, with checks required during and after rain events at minimum. See our ECM inspection checklist.

Q

What should be checked during and after rainfall?

Whether the ECM is functioning effectively, whether silty water is reaching any public drain, and whether immediate rectification is needed.

Q

What is Total Suspended Solids (TSS)?

TSS is a measure of the solid particles suspended in water; it is used to assess how much silt or sediment remains in site discharge after treatment. The applicable discharge standard is set by the Sewerage and Drainage (Surface Water Drainage) Regulations - check the current regulation for the exact figure that applies to your project.

Q

How should silty water be treated?

Through the treatment train set out in the approved ECM plan - typically settlement, and treatment units or polymer dosing where needed - monitored for discharge quality.

Q

Does ECM cover bentonite or slurry wastewater?

No - ECM addresses silty stormwater from rainfall; construction wastewater such as slurry or bentonite from boring or tunnelling needs separate collection and treatment.

Q

What records should be maintained?

ECM operation and maintenance records, inspection findings, and corrective actions, kept available for PUB on request.

Q

When may ECM facilities be removed?

After the QECP verifies that earthworks are complete and the site is fully reinstated.

Q

Does PUB registration remove the need for other approvals?

No - other approvals from relevant agencies may still be required for the same works.

Q

Can the QECP assist with site inspections and rectification?

Yes - this is part of standard QECP involvement through the construction period.

Q

How can I request an ECM assessment?

Contact pe@qp.sg with your project details; scope and requirements are assessed per project.